Town Hall Stormwater Retrofit

Schedule Update
07/10/2012
 
Bids were received on June 14th, 2012. Lucena Brothers Construction of Cumberland Rhode Island was the apparent low bidder.
 
A tentative Notice of Award of Contract is expected to happen by Friday 07-13-12, pending transfer of funds from the Charles River Watershed Association to the Town of Blackstone.
 
If the funds are transferred to the Town within the next few days, a contract could be signed as soon as July 20th.
 
The Superintendent of Public Works will be responsible for the day to day construction supervision and inspection.
 
Our goal is to be substantially complete with the pavement in the parking area before Labor Day. The cisterns, bio-retention areas and plantings will likely be done by late September or early October.
 
During construction various sections of the parking lot behind Town Hall/Senior Center will be closed. Residents are advised to seek alternate parking when doing business or visiting the Municipal Center.